Updated:

A driveway 40 ft long and 10 ft wide with a 4 in layer of gravel is 133.3 cubic feet, or 4.94 cubic yards in place. Add 10% extra and a 1.2 allowance for compaction and you order about 6.5 cu yd, which at a typical planning density is roughly 8.8 short tons.

The formula

Work in feet, convert the depth from inches, then convert cubic feet to cubic yards (1 cu yd = 27 cu ft).

cu ft = length x width x (depth in inches / 12)
cu yd = cu ft / 27
order = cu yd x 1.10 (extra) x 1.2 (compaction)

The 10% extra and the 1.2 compaction factor are planning allowances for a gravel layer (the calculator above starts with them), not rules. Loose gravel packs down when it is compacted, so you need more loose material than the finished layer would suggest. If your supplier or installer uses another allowance, use theirs.

How far one cubic yard goes

Depth Sq ft per cu yd (in place) Sq ft per cu yd ordered (10% extra, 1.2 compaction)
2 in 162 122.7
3 in 108 81.8
4 in 81 61.4
6 in 54 40.9

Driveway sizes at 4 in deep

Driveway Area (sq ft) Cu yd in place Cu yd to order Short tons to order
10 x 20 ft 200 2.47 3.26 4.4
10 x 40 ft 400 4.94 6.52 8.8
12 x 40 ft 480 5.93 7.82 10.5
12 x 60 ft 720 8.89 11.73 15.8

Tons are volume x 1.6 t/m³ (a typical density for gravel and sand) converted to short tons. Real density changes with the stone, its size and moisture, so ask the supplier how many tons they count in a cubic yard. The conversion is covered in how many tons are in a cubic yard of gravel.

Worked example: 40 x 10 ft driveway, 4 in deep

  1. Area: 40 x 10 = 400 sq ft.
  2. Depth in feet: 4 / 12 = 0.3333 ft.
  3. Volume: 400 x 0.3333 = 133.33 cu ft.
  4. Cubic yards: 133.33 / 27 = 4.938 cu yd.
  5. Add 10% extra: 4.938 x 1.1 = 5.432 cu yd.
  6. Add compaction: 5.432 x 1.2 = 6.519 cu yd, so ask for 6.5 cu yd.

In metric: 12.192 m x 3.048 m x 0.1016 m = 3.776 m³ in place, and 4.984 m³ to order.

Gravel under a concrete slab

Gravel under concrete is the same arithmetic with the slab’s footprint. A 12 x 12 ft slab on a 4 in gravel base is 144 sq ft x 4 / 12 = 48 cu ft, or 1.78 cu yd in place and 2.35 cu yd with the extra and compaction. The concrete itself is a separate volume: see how much concrete for a slab. A paver patio base follows the same method, with a sand layer on top; see how many pavers you need.

Common mistakes and waste

  • Skipping the inch conversion. Multiplying feet by inches gives a meaningless number. Divide the depth in inches by 12 first.
  • Ordering the in-place volume. Loose gravel compacts. The in-place figure is what you are building, not what you order.
  • Mixing tons and yards. Quarries often sell by weight and delivery trucks by volume. Convert both ways before you compare quotes.
  • Treating the drive as one rectangle. A curve, a turnaround or a wider apron is easier as separate rectangles added together.
  • Assuming a flat subgrade. Low spots eat gravel. Measure the depth at several points and use the average.
  • Choosing the stone by volume alone. The stone size and type depend on how the surface will be used. Ask the supplier.

Plan the whole job in Gaugo

Gaugo is a construction materials calculator for Android. It works offline for the whole job, so you can add the gravel, a concrete pad and a hauling estimate in one project, and it exports a PDF estimate for a supplier or client. Haul loads are covered in how many cubic yards are in a dump truck. Open the Gaugo construction calculator.

These numbers are planning estimates. Confirm quantities with your supplier or local rules before you order.

FAQ

How much gravel do I need for a driveway?

A 40 x 10 ft driveway 4 in deep is 4.94 cu yd in place. With 10% extra and a 1.2 compaction allowance, order about 6.5 cu yd.

How much gravel do I need under a concrete slab?

A 12 x 12 ft slab on a 4 in gravel base is 1.78 cu yd in place, or about 2.35 cu yd with 10% extra and 1.2 compaction.

How many cubic yards are in a ton of gravel?

At a typical planning density of 1.6 t/m³, one short ton is about 0.74 cu yd. Density varies by stone, so confirm it with your supplier.

How deep should driveway gravel be?

Layers of 4 to 6 in are a common starting range, but soil, traffic and local practice decide it. Check with your supplier or contractor.