How Many Bags of Concrete Do I Need?

Updated:

The number of bags per cubic yard is 27 cubic feet divided by the yield printed on the bag, then rounded up. If a bag says it makes 0.6 cu ft, a yard takes 45 bags; add about 5% for waste.

Why there is no single answer

Bag weights (60 lb, 80 lb and so on) and yields differ between brands and mixes, so no single yield is true for every bag. Yield varies by brand and mix, so use the figure printed on the bag, not the weight.

bags = (volume in cu ft x 1.05) / yield per bag in cu ft, rounded up

Remember that 1 cubic yard = 27 cubic feet.

Bags per cubic yard for different label yields

The yields below are examples to show how the count changes. Replace them with the number on your bag.

Yield on the label Bags per cu yd Bags per cu yd with 5% extra
0.30 cu ft 90.0 95
0.45 cu ft 60.0 63
0.60 cu ft 45.0 48

Bigger bags yield more, so the count drops, but the total weight you carry does not.

Worked example: 1.5 cubic yards

Say you worked out 1.5 cu yd for footings and the bag says 0.6 cu ft.

  1. Volume: 1.5 x 27 = 40.5 cu ft.
  2. Add 5%: 40.5 x 1.05 = 42.5 cu ft.
  3. Bags: 42.5 / 0.6 = 70.9, round up to 71 bags.

At a yield of 0.45 cu ft the same job needs 95 bags, and at 0.30 cu ft it needs 142. For slab volumes, see how much concrete for a slab.

If you mix cement, sand and stone yourself

Gaugo’s default site mix is 1:2:3 (cement : sand : stone by volume), with a dry-volume factor of 1.54, cement at 1 440 kg/m³ and the US cement bag set to 94 lb (42.64 kg). Per cubic yard of finished concrete, before extra:

Mix 94 lb cement bags Sand (cu yd) Stone (cu yd)
1:2:3 6.6 0.51 0.77
1:2:4 5.7 0.44 0.88
1:3:5 4.4 0.51 0.86
1:3:6 4.0 0.46 0.92

The arithmetic for 1:2:3: 1 cu yd = 0.7646 m³, x 1.54 = 1.1774 m³ dry; cement is 1/6, so 0.1962 m³; x 1 440 = 282.6 kg; / 42.64 kg = 6.63 bags. With 5% extra that becomes 6.96, so 7 bags per yard. Always round the total job up, not each step.

Common mistakes and waste

  • Using the weight instead of the yield. Yield differs between brands, so an 80 lb bag does not automatically make a fixed volume. Read the label.
  • Rounding too early. Work out the whole job in cubic feet, then divide, then round up once.
  • No extra. Allow about 5%. Uneven ground, spills and leftover in the mixer add up.
  • Mixing brands. Different brands in one pour can have different yields and set times. Buy the whole count in one go.
  • Ignoring mixer capacity. Check how many bags your mixer can take per batch so the final batch is not a tiny one.

For round holes, such as posts, work out the hole volume first: see how much concrete for a fence post.

Before you buy

Photograph the yield on the bag label in the store. Ask the supplier how many bags a pallet holds, and check that your mixer can take a whole batch, because a batch that is too big sets before you can place it.

Estimate the whole job

Gaugo is a construction materials calculator for Android. It calculates the whole job offline, with no ads, in metric or imperial, and gives you a PDF estimate. Try the Gaugo construction calculator.

These numbers are planning estimates. Check yields and quantities against the bag and your supplier.

FAQ

How many bags of concrete make a cubic yard?

Divide 27 cu ft by the yield printed on your bag. A bag that yields 0.6 cu ft takes 45 bags per yard; one that yields 0.45 cu ft takes 60.

How much concrete is in an 80 lb bag?

Commonly labeled about 0.60 cu ft, which is 45 bags per cubic yard. Yields vary by brand, so check your label.

How much concrete is in a 60 lb bag?

Commonly labeled about 0.45 cu ft, which is 60 bags per cubic yard. It yields less than an 80 lb bag, so you need more bags for the same volume. Check your label.

How many 94 lb cement bags are in a cubic yard of site-mixed concrete?

About 6.6 bags for a 1:2:3 mix, or 7 with 5% extra. See the site-mix table below.