How Much Concrete for a 12x12 Slab

Updated:

A 12x12 ft slab poured 4 in thick needs 48 cubic feet, which is 1.78 cubic yards (1.36 m³). Add 5% for spillage and an uneven base and you should order about 1.87 yd³.

Concrete slab calculator

Concrete volume
1.43 m³
Concrete volume
1.87 yd³

Typical slab volumes (4 in thick)

Volume in cubic feet is length x width x thickness in feet. Divide by 27 to get cubic yards, because 1 cu yd = 27 cu ft.

Slab size Cu ft Cu yd Cu yd with 5% extra
10 x 10 ft (3.05 x 3.05 m) 33.33 1.23 1.30
10 x 12 ft 40.00 1.48 1.56
12 x 12 ft (3.66 x 3.66 m) 48.00 1.78 1.87
20 x 20 ft (6.1 x 6.1 m) 133.33 4.94 5.19

Thickness changes the answer fast. For the same 12x12 ft slab:

Thickness Cu yd Cu yd with 5% extra Sq ft covered by 1 cu yd
4 in 1.78 1.87 81
5 in 2.22 2.33 64.8
6 in 2.67 2.80 54

Worked example: 12x12 ft slab, 4 in thick

  1. Convert the thickness to feet: 4 in / 12 = 0.3333 ft.
  2. Multiply: 12 x 12 x 0.3333 = 48 cu ft.
  3. Convert to yards: 48 / 27 = 1.778 cu yd.
  4. Add 5%: 1.778 x 1.05 = 1.867 cu yd. Round up to 1.9 yd³ when you phone the plant.

In metric: 12 ft = 3.6576 m and 4 in = 0.1016 m, so 3.6576 x 3.6576 x 0.1016 = 1.359 m³, or 1.427 m³ with 5% extra.

If you mix it yourself

With Gaugo’s default 1:2:3 site mix, this slab with 5% extra takes about 13 bags of 94 lb cement. For the mix tables and premixed bag counts, see how many bags of concrete you need per cubic yard.

Common mistakes and waste

  • Forgetting thickness. Many people measure the footprint and guess the depth. Measure the actual form depth in several spots.
  • Mixing units. Feet times inches gives nonsense. Convert inches to feet first, or work everything in inches and divide by 1 728 to get cubic feet.
  • No extra. Subgrade is never perfectly flat, forms flex and some concrete stays in the truck or wheelbarrow. 5% is a sensible starting point; go higher on rough ground.
  • Ordering exactly. Running short mid-pour leaves a cold joint. Running slightly over is cheap by comparison.
  • Ignoring the base. A gravel base under the slab is a separate volume: area x thickness x extra. The paver base example shows the arithmetic.
  • Skipping rebar or mesh. Reinforcement does not change the concrete volume, but it is part of the job and the cost.

The app does the same arithmetic, with metric and imperial inputs, the 5% extra already applied and a total in cubic yards and cubic meters. For a post-hole pour, use how much concrete for a fence post instead, because holes are round.

Before you order

Measure the form depth at the corners and in the middle, and use the average. When you phone the plant, give the volume in cubic yards to one decimal place and ask how they round, whether there is a minimum load and what the delivery charge is. Add thickened edges or a footing as separate volumes.

Estimate the whole job

Gaugo is a construction materials calculator for Android. It calculates the whole job offline, with no ads, and saves a PDF estimate you can send to a supplier or client. See the Gaugo construction calculator.

These numbers are planning estimates. Confirm thickness, mix and quantities with your supplier or designer before ordering.

FAQ

How much concrete do I need for a 10x12 slab?

At 4 in thick, 10 x 12 ft is 40 cu ft, or 1.48 cubic yards. With 5% extra, order about 1.56 yd³.

How much concrete do I need for a 20x20 slab?

At 4 in thick, 20 x 20 ft is 133.3 cu ft, or 4.94 cubic yards. With 5% extra, order about 5.19 yd³.

How much concrete per square foot?

A 4 in slab takes 1/3 cu ft per square foot, so one cubic yard covers 81 sq ft. At 5 in it covers 64.8 sq ft, at 6 in 54 sq ft.

How much extra concrete should I order?

Add about 5% for an even, well-prepped base. Add more if the subgrade is uneven or the forms may bow.