How Many Cubic Yards of Dirt in a Dump Truck?

Updated:

This guide plans with a 10 cubic yard truck, and many dump trucks are quoted somewhere around 10 to 14 cu yd, so ask your hauler for the real figure. Dirt also swells when dug: a hole of 22.2 cu yd in the ground becomes 27.8 cu yd loose, so it takes 3 loads in a 10 cu yd truck.

Excavation calculator

Volume in place
22.22 yd³
Loosened volume
27.78 yd³
Truck loads
3

The formula

bank volume (cu yd) = length x width x depth (ft) / 27
loose volume        = bank volume x (1 + swell)
loads               = loose volume / truck capacity, rounded up

A swell of 25% is a common planning figure. Soil type changes it, so treat it as a starting point. Loads are always rounded up: 2.78 loads means 3 trips.

Loads by volume and truck size

Bank volume is the hole or pile measured in place. Loose volume adds 25% swell.

Bank cu yd Loose cu yd Loads in a 10 cu yd truck 12 cu yd truck 14 cu yd truck
10 12.5 2 2 1
20 25.0 3 3 2
30 37.5 4 4 3
40 50.0 5 5 4
50 62.5 7 6 5

Worked example: 20 x 10 ft hole, 3 ft deep

  1. Volume in cubic feet: 20 x 10 x 3 = 600 cu ft.
  2. Cubic yards: 600 / 27 = 22.22 cu yd in the ground.
  3. Add 25% swell: 22.22 x 1.25 = 27.78 cu yd loose.
  4. Loads: 27.78 / 10 = 2.78, so 3 loads.

With a 12 cu yd truck it is 2.31, so 3 loads, and with a 14 cu yd truck 1.98, so 2. In metric the hole is 16.99 m³ and the loose volume is 21.24 m³. The calculator above uses these numbers.

Other common conversions

  • Wheelbarrow. One cubic yard is 27 cu ft. If your barrow holds about 2 to 3 cu ft heaped (check yours), that is roughly 9 to 14 barrow loads per cubic yard: 27 / 3 = 9 and 27 / 2 = 13.5, rounded up to 14.
  • Truck bed. Multiply the length, width and depth of the load in feet and divide by 27. A bed filled 6 ft x 4 ft x 1.5 ft deep holds 36 cu ft, or 1.33 cu yd. Measure your own bed and the height you will really load.
  • An acre. One acre is 43 560 sq ft. One foot deep over an acre is 43 560 cu ft, or 1 613.3 cu yd, and each inch of depth is 134.4 cu yd.
  • Tons. Weight needs a density. At a typical planning density of 1.6 t/m³, one cubic yard is about 1.35 short tons; see how many tons are in a cubic yard of gravel.

Common mistakes and waste

  • Counting the hole only. Excavated soil is loose and bulkier, so the loads follow the loose volume.
  • Using truck capacity as a weight. Capacity in cubic yards and weight limits are different limits. Wet soil is heavier than dry soil, and a truck can reach its weight limit before the body is full.
  • Rounding loads down. A partial load is still a trip.
  • Forgetting backfill. If part of the soil goes back, subtract it from the haul-away volume. Material you bring in for the base is a separate order; see how much gravel you need.
  • Assuming one truck size. Compare quotes by cubic yards per load, not per trip.

Plan the whole job in Gaugo

Gaugo is a construction materials calculator for Android. It works offline for the whole job: excavation, loads, base material and the concrete that follows can sit in one project, with a PDF estimate to share. For a pour that follows the dig, see how much concrete for a slab. Open the Gaugo construction calculator.

These numbers are planning estimates. Confirm quantities with your supplier or local rules before you order.

FAQ

How many cubic yards are in a dump truck?

Many dump trucks are quoted at roughly 10 to 14 cu yd of loose material. This guide (and the calculator above) starts from 10 cu yd, so ask your hauler for the exact capacity.

How many cubic yards are in a truck bed?

Multiply length x width x load depth in feet and divide by 27. A bed filled 6 x 4 ft and 1.5 ft deep is 36 cu ft, or 1.33 cu yd.

How many cubic yards are in a wheelbarrow?

Far less than one: a barrow holds about 2 to 3 cu ft heaped, so it takes 9 to 14 loads per cubic yard, because 1 cu yd is 27 cu ft. Check your own barrow.

How many cubic yards are in an acre?

An acre is 43 560 sq ft. One foot deep is 1 613.3 cu yd and one inch deep is 134.4 cu yd.

How many cubic yards are in a ton?

It depends on the material. At a typical planning density of 1.6 t/m³, one short ton is about 0.74 cu yd. Ask your supplier for the density they use.