How Many Bags of Mortar per 100 Block

Updated:

One hundred standard 8x8x16 in concrete blocks laid with 3/8 in joints and full mortar bedding use about 4.1 cubic feet of wet mortar (5% extra included). The bag count is that volume divided by the yield printed on your mortar bag: at 0.6 cu ft per bag, 7 bags. If you mix your own at 1:4, it is about 2 bags of 94 lb cement and 4.3 cu ft of sand. Face-shell bedding, normal for hollow block, uses less, so check the “blocks per bag” figure on your bag.

Brick and block wall calculator

Net wall area
88.88 ft²
Bricks/blocks per area
1.13 pcs/ft²
Bricks/blocks needed
105
Mortar volume
0.15 yd³
Cement bags for mortar (1:4)
2
Sand for mortar
0.16 yd³

How the number is found

Mortar fills the space between the units. So the volume is the space the wall occupies minus the space the units fill.

  • The wall is 7-5/8 in thick. Joints show only on the face, so the mortar layer is the face area of a block plus joint, minus the block face, times the wall thickness.
  • Face with joint: 16 x 8 = 128 sq in. Actual block face: 15-5/8 x 7-5/8 = 119.14 sq in.
  • Mortar per block = (128 - 119.14) x 7.625 = 67.55 cu in = 0.0391 cu ft.
  • For 100 blocks: 3.91 cu ft, plus 5% = 4.10 cu ft of wet mortar.

For bricks, one modular brick with a 3/8 in joint on top and one side (and a 3-5/8 in thick wall) has:

  • Space: 8 x 2-5/8 x 3-5/8 in. Brick: 7-5/8 x 2-1/4 x 3-5/8 in.
  • Mortar per brick = 13.93 cu in. For 1 000 bricks: 8.06 cu ft, plus 5% = 8.47 cu ft.

The block figure assumes mortar across the full wall thickness (full bedding). Face-shell bedding on hollow blocks uses less, and this guide does not give a number for it.

Table (3/8 in joints, 5% extra)

Job Wet mortar Cement 1:4 mix (94 lb bags) Sand 1:4 mix
100 blocks 8x8x16 4.1 cu ft 1.02, so 2 4.3 cu ft
1 000 bricks 8.5 cu ft 2.1, so 3 8.8 cu ft

Worked example: 100 blocks, site mix 1:4

Gaugo’s default is a 1:4 cement-to-sand mix by volume, a dry-volume factor of 1.3, and cement at 1 440 kg/m³ (89.9 lb per cu ft). This is an app default, not a US mortar type; if you use masonry cement or type N/S mortar, follow the bag.

  1. Wet mortar: 4.10 cu ft.
  2. Dry volume: 4.10 x 1.3 = 5.34 cu ft.
  3. Cement is 1/5 of it: 1.07 cu ft, x 89.9 lb = 95.9 lb.
  4. Bags of 94 lb: 95.9 / 94 = 1.02, round up to 2 bags.
  5. Sand is 4/5: 5.34 x 0.8 = 4.27 cu ft.

For 1 000 bricks the same steps give 8.47 x 1.3 = 11.0 cu ft dry, 2.2 cu ft cement = 198 lb, which is 2.1 bags, so 3 bags of 94 lb cement and 8.8 cu ft of sand. Round up once, at the end.

If you buy premixed mortar bags

Use the same wet-mortar volume and divide by the yield on the bag label. For example, if the label says 0.6 cu ft per bag: 100 blocks need 4.10 / 0.6 = 6.84, so 7 bags, and 1 000 bricks need 8.47 / 0.6 = 14.1, so 15 bags. That 0.6 is only an example; yields differ by brand, so read the label. Bag weight alone does not tell you the yield.

Common mistakes and waste

  • Quoting bags per block from memory. Rules of thumb differ with block size, joint thickness and bedding. Work from volume.
  • Forgetting waste. Mortar droppings, a mixer that is not scraped clean and mortar that stiffens before use all add up. 5% is a minimum.
  • Mixing too much at once. Mortar stiffens, so mix amounts you can lay in a short time.
  • Using the wrong joint. A 1/2 in joint instead of 3/8 in raises the volume substantially.
  • Forgetting grouted cores. Filled block cores use grout, not bedding mortar, and that is another volume.

To count the units themselves, see how many bricks per square foot and how many bricks to build a house.

Before you mix

Decide the bedding style first, full bed or face-shell only, because it changes the volume more than anything else. Measure the joint on your first course; a joint that creeps from 3/8 in to 1/2 in uses noticeably more mortar.

Estimate the whole job

Gaugo is a construction materials calculator for Android. It calculates the whole job offline, with no ads, and gives a PDF estimate. It includes a mortar calculator. See the Gaugo construction calculator.

These numbers are planning estimates. Confirm mix, yield and quantities with your supplier.

FAQ

How many bags of mortar per 100 blocks?

About 4.1 cu ft of wet mortar for 100 standard 8x8x16 blocks with full 3/8 in bedding and 5% extra. Divide by the yield on your bag: at 0.6 cu ft per bag that is 7 bags. Face-shell bedding uses less.

How many bags of mortar per 1 000 bricks?

About 8.5 cu ft of wet mortar for 1 000 modular bricks. At 0.6 cu ft per premix bag that is 15 bags. Mixing on site at 1:4 instead takes about 3 bags of 94 lb cement plus sand.

How much cement is required for 1 000 bricks?

About 198 lb, which is 2.1 bags of 94 lb cement, so buy 3. This assumes a 1:4 mix and a 1.3 dry factor.

How many bags of mortar per brick?

Roughly 0.0085 cu ft of wet mortar per modular brick, so divide that by the bag yield. At 0.6 cu ft per bag that is about 1 bag per 70 bricks.